| Risk Register for the LCG Project — 8th August 2003 | ||||||||||||||||||||||
| Likelihood: | Impact: | |||||||||||||||||||||
| 1 - never expected to happen | 1 - we can deal with it, no problem | |||||||||||||||||||||
| 2 - could happen but very unlikely | 2 - a bit of a hassle but not too bad | |||||||||||||||||||||
| 3 - could well happen at some point | 3 - clearly can be dealt with, but with significant effort | |||||||||||||||||||||
| 4 - will probably happen | 4 - crisis | |||||||||||||||||||||
| ID | Name | LCG | Funding | Apps | Fabric | Deploy. | GTA | |||||||||||||||
| Li | Im | Risk | Li | Im | Risk | Li | Im | Risk | Li | Im | Risk | Li | Im | Risk | Li | Im | Risk | |||||
| Personnel Issues | LCG | Funding | Apps | Fabric | Deploy. | GTA | ||||||||||||||||
| R1 | Recruitment/Retention difficulties | 1 | 2 | 2 | 2 | 2 | 4 | 3 | 3 | 9 | 1 | 2 | 2 | 3 | 3 | 9 | ||||||
| R2 | Sudden loss of key staff | 2 | 3 | 6 | 2 | 3 | 6 | 2 | 3 | 6 | 2 | 3 | 6 | 2 | 3 | 6 | ||||||
| R3 | Sub-components not delivered to area | 2 | 2 | 4 | 2 | 3 | 6 | 2 | 4 | 8 | ||||||||||||
| R4 | Duplication of Effort | 2 | 1 | 2 | 4 | 1 | 4 | 1 | 2 | 2 | ||||||||||||
| Schedule and Budgets | LCG | Funding | Apps | Fabric | Deploy. | GTA | ||||||||||||||||
| R5 | Unrealistic timeframe/schedule | 3 | 2 | 6 | 3 | 3 | 9 | 3 | 3 | 9 | ||||||||||||
| R6 | LHC timeframe extended | 3 | 1 | 3 | 3 | 1 | 3 | |||||||||||||||
| R7 | Lack of funding to meet phase 1 goals | 2 | 3 | 6 | 2 | 3 | 6 | 2 | 4 | 8 | ||||||||||||
| R8 | Funding agencies do not provide agreed resources | 1 | 3 | 3 | 1 | 3 | 3 | |||||||||||||||
| R9 | Offered in kind contributions do not fit requirements | 2 | 2 | 4 | 2 | 2 | 4 | 2 | 2 | 4 | ||||||||||||
| Requirements and Analysis | LCG | Funding | Apps | Fabric | Deploy. | GTA | ||||||||||||||||
| R10 | Change in project scope | 2 | 1 | 2 | 2 | 2 | 4 | 2 | 2 | 4 | 2 | 2 | 4 | |||||||||
| R11 | Conflicting software requirements | 2 | 2 | 4 | 2 | 3 | 6 | 2 | 3 | 6 | 2 | 3 | 6 | |||||||||
| R12 | Inadequate analysis/specification | 2 | 3 | 6 | 2 | 2 | 4 | 2 | 4 | 8 | 2 | 4 | 8 | |||||||||
| R13 | Requirements/Functionality mismatch | 2 | 3 | 6 | 2 | 2 | 4 | 2 | 3 | 6 | 2 | 4 | 8 | 1 | 3 | 3 | ||||||
| Problems with software components | LCG | Funding | Apps | Fabric | Deploy. | GTA | ||||||||||||||||
| R14 | Inadequate or late 3rd party software | 3 | 3 | 9 | 3 | 2 | 6 | 1 | 1 | 1 | 4 | 4 | 16 | 2 | 4 | 8 | ||||||
| R15 | 3rd party software no longer available or not maintainable | 2 | 2 | 4 | 3 | 2 | 6 | 1 | 1 | 1 | ||||||||||||
| R16 | Software maintainability problems | 2 | 3 | 6 | 1 | 2 | 2 | 2 | 4 | 8 | 2 | 3 | 6 | |||||||||
| R17 | Licensing Limitiations | 3 | 2 | 6 | 3 | 4 | 12 | |||||||||||||||
| R18 | Deployment/integration failure | 1 | 2 | 2 | 1 | 3 | 3 | |||||||||||||||
| Performance shortfalls | LCG | Funding | Apps | Fabric | Deploy. | GTA | ||||||||||||||||
| R19 | Reliability problems | 3 | 3 | 9 | 3 | 3 | 9 | 3 | 4 | 12 | ||||||||||||
| R20 | Scalability problems | 3 | 3 | 9 | 4 | 3 | 12 | 3 | 4 | 12 | ||||||||||||
| R21 | Grid Middleware/Infrastructure failure | 3 | 3 | 9 | 3 | 3 | 9 | 3 | 4 | 12 | ||||||||||||
| Straining capabilities | LCG | Funding | Apps | Fabric | Deploy. | GTA | ||||||||||||||||
| R22 | Technology shifts | 1 | 4 | 4 | 4 | 2 | 8 | 1 | 4 | 4 | ||||||||||||
| R23 | Standards not established sufficiently quickly | 3 | 1 | 3 | 3 | 3 | 9 | |||||||||||||||
| R24 | Competing developments creates confusion | 3 | 1 | 3 | 3 | 3 | 9 | |||||||||||||||
| R25 | Security model inadequate to operate Grid | 2 | 3 | 6 | 2 | 3 | 6 | 2 | 3 | 6 | ||||||||||||
| Grid Operations | LCG | Funding | Apps | Fabric | Deploy. | GTA | ||||||||||||||||
| R26 | Site/LCG Requirement Mismatch | 2 | 4 | 8 | 2 | 4 | 8 | |||||||||||||||
| R27 | Sites do not deliver agreed services | 2 | 2 | 4 | 2 | 2 | 4 | |||||||||||||||
| R28 | Site security requirements too restrictive | 3 | 3 | 9 | 3 | 4 | 12 | |||||||||||||||
| R29 | Inadequate operational support | 2 | 3 | 6 | 2 | 4 | 8 | |||||||||||||||
| R30 | Inadequate user support | 2 | 3 | 6 | 2 | 4 | 8 | |||||||||||||||
| CERN Tier0/Tier1 | LCG | Funding | Apps | Fabric | Deploy. | GTA | ||||||||||||||||
| R31 | Inadequate power and hvac arrangements | 3 | 3 | 9 | 3 | 4 | 12 | |||||||||||||||
| R32 | Purchasing delays | 2 | 3 | 6 | 2 | 4 | 8 | |||||||||||||||
| R33 | Inadequate wide area networking | 1 | 3 | 3 | 1 | 3 | 3 | |||||||||||||||
| R34 | Inadequate local area networking | 2 | 3 | 6 | 2 | 3 | 6 | |||||||||||||||
| R35 | Storage technology limitations | 2 | 3 | 6 | 2 | 4 | 8 | |||||||||||||||
| Political | LCG | Funding | Apps | Fabric | Deploy. | GTA | ||||||||||||||||
| R36 | Failure of international cooperation | 1 | 4 | 4 | 2 | 4 | 8 | 2 | 4 | 8 | ||||||||||||
| R37 | Lack of cooperation between Tier centres | 1 | 4 | 4 | 1 | 4 | 4 | |||||||||||||||
| R38 | Bad publicity | 2 | 2 | 4 | ||||||||||||||||||
| R39 | Withdrawal of an experiment | 1 | 4 | 4 | 2 | 3 | 6 | |||||||||||||||
| R40 | Non take up of project results | 2 | 2 | 4 | 2 | 2 | 4 | 2 | 2 | 4 | ||||||||||||
| R41 | Misunderstanding about project goals/intent | 2 | 3 | 6 | 2 | 3 | 6 | |||||||||||||||