Tender for Tape Servers
General Info
| IT-3419/IT |
| Equipment required for 21-Dec-05 |
| Equipment expected by 13-Jan-06 |
|
MS-3293/IT |
| not needed |
Step-by-Step Status
| Tender docs prepared |
14-Sep-05 |
15-Sep-05 |
| Spec meeting held |
21-Sep-05 |
21-Sep-05 |
| Documents issued |
23-Sep-05 |
28-Sep-05 |
| Envelope opening date set |
24-Oct-05 |
|
| Offers received |
26-Oct-05 |
|
| Offers opened |
02-Nov-05 |
|
| Initial compliance verified |
04-Nov-05 |
|
| Detailed hardware tests completed |
11-Nov-05 |
|
| Adjudication |
11-Nov-05 |
|
| Contract/final price negotiated |
11-Nov-05 |
|
| Order prepared |
11-Nov-05 |
|
| Order sent |
18-Nov-05 |
|
| Equipment arrives |
05-Jan-06 |
|
| Physical installation complete |
06-Jan-06 |
|
| Stress testing complete |
13-Jan-06 |
|
| Commission |
13-Jan-06 |
|
| Pay the bill |
13-Feb-06 |
|
|
Market Survey for Physics computing equipment
General Info
Step-by-Step Status
| Announced to FC |
07-Oct-05 |
14-Jun-05 |
| MS prepared |
21-Nov-05 |
|
| MS docs reviewed in IT |
30-Nov-05 |
|
| Spec meeting for MS help |
09-Dec-05 |
|
| MS issued |
15-Dec-05 |
|
| Deadline for MS replies |
03-Feb-06 |
|
| MS replies analysed |
17-Feb-06 |
|
| Commission |
17-Feb-06 |
|
| MS Expires |
17-Feb-07 |
|
|