|
|
LHC
Computing Grid Deployment Schedule 2006-08
|

CERN must be capable of accepting data from the
experiment data acquisition (DAQ) systems and recording it on magnetic tape at
a long term sustained average rate of 1.6 GBytes/sec during the proton run and
1.85 GBytes/sec during the ions run. During 2004 the disk-tape writing rate was
demonstrated at 1 GByte/sec. In March 2005 the recording rate for simulated DAQ
through mass storage system to tape was demonstrated at 450 MBytes/sec. The
target DAQ-mass-storage-tape rate achievable at the end of December 2005 is 750
MBytes/sec, rising to the full nominal data rate of 1.6 GBytes/sec by August
2006. These demonstrations must be performed in parallel with the Service Challenge activities described
below.
The goal of Service Challenge 2 is to demonstrate reliable file transfer, disk
to disk, between CERN and at least 5 Tier-1 centres, sustaining for one week an
aggregate throughput of 500 MBytes/sec at CERN.
The minimum capability at each Tier-1 is 100 MBytes/sec. The Tier-1 sites
taking part are BNL, CNAF, FNAL, GridKA, IN2P3, NIKHEF/SARA and RAL.
The service should use the initial
version of the reliable file transfer service, provided by CERN.
The target is to complete this
challenge by end April 2005.
Service Challenge 3 operates a reliable base service including most of the Tier-1 centres
and some Tier-2s. It has two phases – a setup phase terminating with a
throughput test, followed by a three-month period of stable operation during
which experiments may carry out tests of their software chains and computing
models.
The throughput goals at each Tier-1
are 150 MBytes/sec network-disk, and 60 MBytes/sec network-tape, with CERN
capable of supporting 1 GByte/sec disk-network.
The goal of the throughput test is
to maintain for one week an average throughput of 400 MBytes/sec from disk at
CERN to tape at the Tier-1 sites. The
Tier-1 sites taking part are ASCC, BNL, CNAF, FNAL, GridKA, IN2P3, NIKHEF/SARA,
RAL and Triumf. The target date for completing the throughout test is end July
2005.
The service phase of Service
Challenge 3 will include additional software components, including a grid
workload management system, grid catalog, mass storage management services and
Virtual Organisation (VO) management services. A small number of Tier-2 sites
will also be involved, each supported by a Tier-1 centre. The initial list of
participating Tier-2 centres and their supporting Tier-1s is given in the table
below. The service phase is scheduled to operate for three months from
September to December 2005.
|
Tier-2 / Federation |
Tier1 |
Experiment |
|
|
CNAF, |
CMS |
|
|
CNAF, |
|
|
DESY, |
|
ATLAS, CMS |
|
|
|
ATLAS |
|
|
|
CMS |
|
|
|
LHCb |
|
US Tier2s |
BNL / FNAL |
ATLAS / CMS |
Table 1: Core Set of Tier-2 Centres in Service Challenge 3
Service Challenge 4 aims to demonstrate that all of the offline data processing
requirements expressed in the experiments’ Computing Models, from raw data
taking through to analysis, can be handled by the Grid at the full nominal data
rate of the LHC. All Tier1 sites will be involved, together with the majority
of the Tier2s. The challenge must complete at least 6 months prior to first
data taking, when it will become the production service for LHC and is made
available to the experiments for final testing, commissioning and processing of
cosmic ray data.
The setup phase ends with a
throughput demonstration sustaining for three weeks the target data rates at
each site as defined in the following table. The throughput is measured
network-tape at each Tier-1, and disk-network at CERN. The target date for
completing the throughput test is end April 2006.
|
Centre |
|
ATLAS |
CMS |
LHCb |
Target Data Rate MBytes/sec |
|
ASCC |
|
X |
X |
|
110 |
|
CNAF |
X |
X |
X |
X |
220 |
|
PIC |
|
X |
X |
X |
200 |
|
CC-IN2P3 |
X |
X |
X |
X |
220 |
|
GridKA |
X |
X |
X |
X |
220 |
|
RAL |
X |
X |
X |
X |
220 |
|
BNL |
|
X |
|
|
65 |
|
FNAL |
|
|
X |
|
50 |
|
TRIUMF |
|
X |
|
|
65 |
|
NIKHEF/SARA |
X |
X |
|
X |
175 |
|
NORDIC
DATA GRID FACILITY |
X |
X |
|
|
90 |
|
Target
data rate at CERN |
1,600 |
||||
Table 2 – Nominal Network/Tape Data Rates by Site
The service phase of Service
Challenge 4 will include the basic software components required for the initial
LHC data processing service, as defined in the LCG Technical Design Report. The
service must be able to support the full computing model of each experiment,
including simulation and end-user batch analysis at Tier-2 centres. The service
phase is scheduled to operate for four months from May to September 2006.
The initial LHC service is scheduled
to enter operation by end September 2006, capable of handling the full nominal
data rate (see Table 2). The service will be used for extended testing of the
computing systems of the four experiments, for simulation and for processing of
cosmic data. During the following six months each site will build up to the
full throughput needed for LHC operation, twice the nominal data rate.