Version 2003.07/4
This is a summary of the Level-1 and Level-2 Milestones for the LHC Computing Grid Project LCG as presented in the quarterly report of July 2003.
Applications
Fabrics
GRID Technology
GRID Deployment
Level-1 Milestones
The Level-1 and Level-2 Milestones constitute the baseline planning
for the LCG as of July 2003.
The unique identifier is in column 2.
The milestone level is given column 3.
The column 5 (Date_MS) gives the baseline date when the milestone is due and
column 6 (MS_Done) gives the date when a milestone was achieved.
Hyperlinks to more detailed information (column 7)
are currently available for the applications and Grid deployment areas and for the
Level-1
milestones. For the rest this information will be provided in the near future.
Full planning information is available as
MS-Project file.
The time evolution of the Milestones is given in a chart.
| WBS | ID_Unique | MS_Lvl |
Name | Date_MS | MS_Done | Hyperlink |
|---|---|---|---|---|---|---|
| 1 |
LHC Computing Grid Project | |||||
| 1.1 |
Applications | |||||
| 1.1.1 |
Software Process and Infrastructure (SPI) | |||||
| 1.1.1 | 1.156 | 2 |
Initial process and infrastructure team in place | 15-04-2002 | 14-07-2002 | More Info |
| 1.1.1 | 1.158 | 2 |
Basic LCG code development and repository services in place | 01-05-2002 | 02-05-2002 | More Info |
| 1.1.1 | 1.159 | 2 |
Software process workplan to SC2 | 11-10-2002 | 11-10-2002 | More Info |
| 1.1.1 | 1.16 | 2 |
All infrastructure tools and services in beta | 31-12-2002 | 09-02-2003 | More Info |
| 1.1.1 | 1.161 | 2 |
All infrastructure tools and services released (SPI V1.0) | 28-02-2003 | 28-02-2003 | More Info |
| 1.1.1 | 1.162 | 2 |
2003 SPI workplan complete | 30-05-2003 | 29-06-2003 | More Info |
| 1.1.1 | 1.163 | 2 |
Software library complete | 31-05-2003 | 01-05-2003 | More Info |
| 1.1.1 | 1.164 | 2 |
Savannah based portal complete | 31-05-2003 | 22-12-2002 | More Info |
| 1.1.1 | 1.17 | 2 |
SPI support for Windows binary version of LCG software | 15-08-2003 | More Info | |
| 1.1.2 |
Physics data management (POOL) | |||||
| 1.1.2 | 1.109 | 2 |
2003 persistency framework workplan complete | 24-02-2003 | 05-03-2003 | More Info |
| M1.2 | M1.2 | 1 |
General release of POOL hybrid data store | 15-06-2003 | 30-06-2003 | More Info |
| 1.1.2 | 1.176 | 2 |
CMS POOL integration: POOL persistency of CMS event | 31-07-2003 | More Info | |
| 1.1.2 | 1.177 | 2 |
ATLAS POOL integration: POOL persistency in Release 7 | 21-08-2003 | More Info | |
| 1.1.2 | 1.181 | 2 |
POOL support for Windows binaries | 30-09-2003 | More Info | |
| 1.1.2 | 1.179 | 2 |
ATLAS POOL validation with DC1 data | 31-10-2003 | More Info | |
| 1.1.2 | 1.18 | 2 |
CMS POOL validation with PCP data | 31-10-2003 | More Info | |
| 1.1.2 | 1.117 | 2 |
2004-2005 persistency framework workplan complete | 15-12-2003 | More Info | |
| M1.7 | M1.7 | 1 |
Full function release of persistency framework | 01-03-2005 | More Info | |
| 1.1.2.1 |
POOL Persistency Framework | |||||
| 1.1.2.1 | 1.101 | 2 |
Hybrid event store workshop | 05-06-2002 | 05-06-2002 | More Info |
| 1.1.2.1 | 1.102 | 2 |
Persistency framework status report | 18-06-2002 | 18-06-2002 | More Info |
| 1.1.2.1 | 1.103 | 2 |
Persistency framework workplan to SC2 | 12-07-2002 | 02-08-2002 | More Info |
| 1.1.2.1 | 1.104 | 2 |
V0.1 POOL internal release | 30-09-2002 | 02-10-2002 | More Info |
| 1.1.2.1 | 1.105 | 2 |
V0.2 POOL internal release | 31-10-2002 | 15-11-2002 | More Info |
| 1.1.2.1 | 1.106 | 2 |
First prototype (V0.3) release of POOL hybrid data store | 15-12-2002 | 18-12-2002 | More Info |
| 1.1.2.1 | 1.108 | 2 |
SPI compliance of POOL | 28-02-2003 | 07-03-2003 | More Info |
| 1.1.2.1 | 1.11 | 2 |
POOL V0.4 'interface-complete' release | 28-02-2003 | 07-03-2003 | More Info |
| 1.1.2.1 | 1.111 | 2 |
Define feature set of first general release of POOL | 01-03-2003 | 05-03-2003 | More Info |
| 1.1.2.1 | 1.112 | 2 |
POOL V1.0 pre-production release | 30-04-2003 | 13-05-2003 | More Info |
| 1.1.2.1 | 1.113 | 2 |
Nightly builds deployed in POOL | 30-05-2003 | 29-06-2003 | More Info |
| 1.1.2.1 | 1.114 | 2 |
Initial POOL deployment on LCG-1 | 31-07-2003 | More Info | |
| 1.1.2.1 | 1.116 | 2 |
POOL RDBMS independence layer in beta | 30-09-2003 | More Info | |
| 1.1.2.1 | 1.121 | 2 |
POOL hierarchical cataloging production release | 15-03-2004 | More Info | |
| 1.1.2.1 | 1.12 | 2 |
Release of POOL implementation of conditions DB | 31-03-2004 | More Info | |
| 1.1.2.1 | 1.122 | 2 |
POOL meets scalability requirements | 31-10-2004 | ||
| 1.1.2.2 |
Conditions database | |||||
| 1.1.2.2 | 1.115 | 2 |
POOL implementation of conditions DB - beta | 01-11-2003 | More Info | |
| 1.1.3 |
Core libraries and services (SEAL) | |||||
| 1.1.3 | 1.123 | 2 |
Establish core libraries and services (SEAL) project | 30-10-2002 | 30-10-2002 | More Info |
| 1.1.3 | 1.125 | 2 |
Define the V1 SEAL software suite | 30-11-2002 | 30-11-2002 | More Info |
| 1.1.3 | 1.107 | 2 |
Prototype object dictionary service released | 01-12-2002 | 18-12-2002 | More Info |
| 1.1.3 | 1.126 | 2 |
Present the initial SEAL workplan to SC2 | 10-01-2003 | 10-01-2003 | More Info |
| 1.1.3 | 1.127 | 2 |
SEAL V1 essentials in alpha | 31-03-2003 | 07-04-2003 | More Info |
| 1.1.3 | 1.129 | 2 |
SEAL V0.3 internal release | 16-05-2003 | 24-05-2003 | More Info |
| 1.1.3 | 1.128 | 2 |
Nightly builds deployed in SEAL | 30-06-2003 | More Info | |
| 1.1.3 | 1.13 | 2 |
SEAL V1 release | 30-06-2003 | More Info | |
| 1.1.3 | 1.184 | 2 |
Math library workplan in place | 31-07-2003 | ||
| 1.1.3 | 1.124 | 2 |
Establish external software decision process | 15-09-2003 | More Info | |
| 1.1.3 | 1.187 | 2 |
SEAL support for Windows binaries | 15-09-2003 | More Info | |
| 1.1.3.8 |
Mathematical libraries | |||||
| 1.1.3.8 | 1.167 | 2 |
Delivery of first round of GSL enhancements | 30-05-2003 | More Info | |
| 1.1.4 |
Physicist Interface (PI) | |||||
| 1.1.4 | 1.149 | 2 |
Establish physicist interface project | 19-11-2002 | 25-11-2002 | More Info |
| 1.1.4 | 1.15 | 2 |
Report on PI experiment consultations | 20-01-2003 | 20-01-2003 | More Info |
| 1.1.4 | 1.151 | 2 |
Initial PI plan presented to SC2 | 29-01-2003 | 07-02-2003 | More Info |
| 1.1.4 | 1.152 | 2 |
AIDA interface review (developers) completed | 30-05-2003 | 30-05-2003 | More Info |
| 1.1.4 | 1.153 | 2 |
Physicist interface (PI) workplan completed | 01-07-2003 | 04-07-2003 | More Info |
| 1.1.4 | 1.171 | 2 |
AIDA interface review (users) completed | 15-09-2003 | More Info | |
| 1.1.5 |
Simulation | |||||
| 1.1.5 | 1.131 | 2 |
SC2 mandate for simulation project | 07-12-2002 | 07-12-2002 | More Info |
| 1.1.5 | 1.132 | 2 |
Simulation project structure defined | 28-01-2003 | 28-01-2003 | More Info |
| 1.1.5 | 1.133 | 2 |
Simulation project draft workplan | 28-02-2003 | 28-02-2003 | More Info |
| 1.1.5 | 1.134 | 2 |
Simulation project initial workplan approved | 14-03-2003 | 19-03-2003 | More Info |
| 1.1.5.1 |
Generic simulation framework | |||||
| 1.1.5.1 | 1.139 | 2 |
Generic framework high level design and implementation approach defined | 31-07-2003 | More Info | |
| 1.1.5.1 | 1.144 | 2 |
Generic simulation framework prototype available (G4 and FLUKA) | 31-12-2003 | More Info | |
| 1.1.5.1 | 1.147 | 2 |
First generic simulation framework production release | 01-10-2004 | More Info | |
| 1.1.5.4 |
Physics validation | |||||
| 1.1.5.4 | 1.136 | 2 |
Test beam setup of the four experiments available in G4 | 31-05-2003 | 31-05-2003 | More Info |
| 1.1.5.4 | 1.14 | 2 |
Simulation physics requirements revisited | 31-07-2003 | More Info | |
| 1.1.5.4 | 1.143 | 2 |
First cycle of EM physics validation complete | 30-09-2003 | More Info | |
| 1.1.5.4 | 1.145 | 2 |
First cycle of hadronic physics validation complete | 31-01-2004 | More Info | |
| 1.1.5.4 | 1.146 | 2 |
Simulation test and benchmark suite available | 31-03-2004 | More Info | |
| 1.1.5.4 | 1.148 | 2 |
Final physics validation document complete | 31-12-2004 | More Info | |
| 1.1.5.6 |
Generator services | |||||
| 1.1.5.6 | 1.138 | 2 |
Generator librarian and alpha version of support infrastructure in place | 30-06-2003 | 30-06-2003 | More Info |
|
Fabrics Area |
||||||
| WBS | ID_Unique | MS_Lvl |
Name |
Date_MS | MS_Done | Hyperlink |
| 1.2 |
Fabrics | |||||
| 1.2.1 |
Repositories and Managed Storage | |||||
| 1.2.1.1 |
Castor | |||||
| 1.2.1.1.1 | 2.521 | 2 |
Concept of pluggable scheduler and high rate request handling demonstrated | 01-10-2003 | ||
| 1.2.1.1.2 | 2.520 | 2 |
Integrated prototype of the whole system
| 02-02-2004 | ||
| 1.2.1.1.3 | 2.519 | 2 |
Production system ready for deployment
| 01-04-2004 | ||
| 1.2.1.1.4 | 2.518 | 2 |
Full functional CASTOR release available | 01-03-2005 | ||
| 1.2.1.2 |
Data Recording Challenges | |||||
| 1.2.1.2.1 | 2.516 | 2 |
ALICE DC5 (300 MB/sec) | 01-10-2003 | ||
| 1.2.1.2.2 | 2.515 | 2 |
ALICE DC6 (450 MB/sec) | 01-10-2004 | ||
| 1.2.1.2.3 | 2.514 | 2 |
ALICE DC7 (750 MB/sec) | 03-10-2005 | ||
| 1.2.1.3 |
Evaluation of new tape hardware | |||||
| 1.2.1.3.1 | 2.526 | 2 |
Report on LTO evaluation delivered | 01-03-2004 | ||
| 1.2.1.3.2 | 2.525 | 2 |
Report on high-end tape drive evaluation delivered | 01-12-2004 | ||
| 1.2.1.3.3 | 2.524 | 2 |
Proposal on storage architecture and implementation of disk storage system for Phase 2 made | 01-06-2004 | ||
| 1.2.2 |
Fabric Management | |||||
| 1.2.2.1 | 2.538 | 2 |
SPMA – full production | 01-08-2003 | ||
| 1.2.2.2 | 2.537 | 2 |
NCM – full production | 03-11-2003 | ||
| 1.2.2.3 | 2.536 | 2 |
SMS – initial system | 01-10-2003 | ||
| 1.2.2.4 | 2.535 | 2 |
SMS – full production | 07-01-2004 | ||
| 1.2.2.5 | 2.534 | 2 |
Monitoring – Systems monitor displays operational | 01-10-2003 | ||
| 1.2.2.6 | 2.533 | 2 |
Monitoring – No further need for private (experiment) monitoring | 01-03-2004 | ||
| 1.2.2.7 | 2.532 | 2 |
FT – development started | 01-09-2003 | ||
| 1.2.2.8 | 2.531 | 2 |
FT – Initial system available | 01-03-2004 | ||
| 1.2.2.9 | 2.530 | 2 |
FT – Deployment complete | 01-09-2004 | ||
| 1.2.2.10 | 2.529 | 2 |
HSM ops display – development started | 01-10-2003 | ||
| 1.2.2.11 | 2.528 | 2 |
HSM ops display – system complete | 01-12-2003 | ||
| 1.2.3 |
Computer Centre Upgrade | |||||
| 1.2.3.1 | 2.553 | 2 |
Vault converted to machine room | 01-11-2002 | 01-11-2002 | |
| 1.2.3.2 | 2.552 | 2 |
Right half of m/c room migrated to vault | 01-08-2003 | ||
| 1.2.3.3 | 2.551 | 2 |
Sub-station civil engineering starts | 01-09-2003 | ||
| 1.2.3.4 | 2.550 | 2 |
Sub-station civil engineering finishes | 01-03-2004 | ||
| 1.2.3.5 | 2.549 | 2 |
Sub-station electrical installation starts | 01-04-2004 | ||
| 1.2.3.6 | 2.548 | 2 |
Sub-station commissioned | 07-01-2005 | ||
| 1.2.3.7 | 2.547 | 2 |
Electrical distribution on right side of m/c room upgraded | 02-02-2004 | ||
| 1.2.3.8 | 2.546 | 2 |
Left half of m/c room emptied | 02-08-2004 | ||
| 1.2.3.9 | 2.545 | 2 |
Electrical distribution on left side of m/c room upgraded | 01-06-2005 | ||
| 1.2.3.10 | 2.544 | 2 |
Machine room HVAC upgraded | 01-03-2005 | ||
| 1.2.3.11 | 2.543 | 2 |
New 800KW UPS for physics installed | 03-04-2006 | ||
| 1.2.3.12 | 2.542 | 2 |
Current UPS area re-modelled | 01-01-2007 | ||
| 1.2.3.13 | 2.541 | 2 |
2nd 800 KW UPS added | 02-04-2007 | ||
| 1.2.3.14 | 2.540 | 2 |
3rd 800 KW UPS added | 01-04-2008 | ||
| 1.2.4 |
Batch Computing | |||||
| 1.2.4.1 | 2.564 | 2 |
Baseline plan for Phase 2 agreed (architecture + technology) | 01-06-2004 | ||
| 1.2.4.2 |
Grid Integration | |||||
| 1.2.4.2.1 | 2.562 | 2 |
10 LXBATCH nodes integrated in LCG-1 (isolated from main LXBATCH) | 01-08-2003 | ||
| 1.2.4.2.2 | 2.561 | 2 |
100 LXBATCH nodes integrated in LCG-1 (isolated from main LXBATCH) | 01-10-2003 | ||
| 1.2.4.2.3 | 2.560 | 2 |
Full integration of LXBATCH worker nodes in LCG-1 completed | 01-12-2003 | ||
| 1.2.4.3 |
Batch Scheduling | |||||
| 1.2.4.3.1 | 2.557 | 2 |
Decision on Phase 2 Batch Scheduling System made | 01-12-2004 | ||
| 1.2.5 |
Installation Schedule (short term) | |||||
| 1.2.5.9 |
Networking infrastructure | |||||
| 1.2.5.9.3 | 2.580 | 2 |
Integration of 10 Gbit equipment into the Prototype done | 01-07-2003 | 01-07-2003 | |
| 1.2.5.9.5 | 2.582 | 2 |
First phase of backbone replacement by 10 Gbit equipment | 01-07-2004 | ||
| 1.2.5.9.6 | 2.583 | 2 |
Backbone fully upgraded to 10 Gbit | 01-07-2005 | ||
| 1.2.6 |
Phase 2 Acquisition Process | |||||
| 1.2.6.1 | 2.591 | 2 |
Decisions on the equipment selection criteria made | 01-12-2003 | ||
| 1.2.6.2 | 2.590 | 2 |
Agreement with SPL on acquisition strategy ready | 01-12-2003 | ||
| 1.2.6.3 | 2.589 | 2 |
Market survey issued for cpu and disk | 01-07-2004 | ||
| 1.2.6.4 | 2.588 | 2 |
Market survey issued for tape system | 01-12-2004 | ||
| 1.2.6.5 | 2.587 | 2 |
Phase 2 TDR ready | 01-07-2005 | ||
| 1.2.6.6 | 2.586 | 2 |
Finance Committee for cpu & disk vendor selection passed | 01-09-2005 | ||
| 1.2.6.7 | 2.585 | 2 |
Finance Committee for tape system selection passed | 01-12-2005 | ||
| 1.2.6.8 | 2.584 | 2 |
All orders placed for 2006 equipment | 01-03-2006 | ||
| 1.2.6.9 | 2.575 | 2 |
Order placed for tape system | 09-01-2006 | ||
| 1.2.6.10 | 2.574 | 2 |
2006 system installation and commissioning complete | 01-08-2006 | ||
| 1.2.6.11 | 2.573 | 2 |
Phase 2 service in production | 01-09-2006 | ||
| 1.2.7 |
Milestones prior to June 2003 | |||||
| 1.2.1.7 | 2.599 | 2 |
L2M Production Pilot I starts | 15-01-2003 | 06-01-2003 | |
|
Grid Technology Area |
||||||
| WBS | ID_Unique | MS_Lvl |
Name |
Date_MS | MS_Done | Hyperlink |
| 1.3 |
Grid Technology Area | |||||
| 1.3.1 |
Technology Review | |||||
| 1.3.1.3 | 3.496 | 2 |
Report on the Review of Grid Technologies 2003 ready | 06-10-2003 | ||
| 1.3.1.5 | 3.498 | 2 |
Report on the Review of Grid Technologies 2004 ready | 02-11-2004 | ||
| 1.3.2 |
System Modeling | |||||
| 1.3.2.2 | 3.337 | 2 |
Modeling plan for work during 2003 created | 15-07-2003 | ||
| 1.3.4 |
LCG Technology Evolution | |||||
| 1.3.4.2 | 3.344 | 2 |
Report on GT3 capabilities ready | 01-09-2003 | ||
LCG - EGEE Coordination | ||||||
| 1.3.4.1 | 3.501 | 2 |
EGEE senior management appointed | 15-07-2003 | ||
| 1.3.4.2 | 3.502 | 2 |
Technical design eam established | 01-09-2003 | ||
| 1.3.4.3 | 3.503 | 2 |
2004 "blueprint" architecture published | 01-10-2003 | ||
| 1.3.4.4 | 3.504 | 2 |
Work packages definition published | 03-11-2003 | ||
| 1.3.4.5 | 3.505 | 2 |
Implementation teams, allocations to work packages, team management and job descriptions identified | 03-11-2003 | ||
| 1.3.4.6 | 3.506 | 2 |
2004 work plan and system performance goals for 2004 by trimester published | 01-12-2003 | ||
| 1.3.4.7 | 3.507 | 2 |
Work plan formally agreed | 15-12-2003 | ||
| 1.3.5 |
TDR Planning | |||||
| 1.3.5.2 | 3.347 | 2 |
Plan and outline for the TDR available | 01-10-2004 | ||
| 1.3.5.3 | 3.348 | 2 |
Proposal for review created | 01-03-2005 | ||
| 1.3.5.4 | 3.349 | 2 |
LCG TDR completed | 01-06-2005 | ||
| 1.3.7 |
Milestones prior to June 03 | |||||
| 1.3.7.3 | 0 |
Deliver initial software packages | ||||
| 1.3.7.3.2 | 3.494 | 2 |
Initial software packages delivered | 30-05-2003 | 30-05-2003 | |
|
Grid Deployment Area |
||||||
| WBS | ID_Unique | MS_Lvl |
Name |
Date_MS | MS_Done | Hyperlink |
| 1.4 |
Grid Deployment | |||||
| 1.4.1 |
First Global Service Initial Availability | |||||
| 1.4.1.1 | 4.353 | 2 |
Initial middleware for LCG-1 delivered
| 30-04-2003 | More Info | |
| 1.4.1.2 | 4.354 | 2 |
LCG-1 security model implemented | 30-06-2003 | 30-06-2003 | More Info |
| 1.4.1.3 | 4.355 | 2 |
First prototype operations & user support service in place | 30-06-2003 | 30-06-2003 | More Info |
| 1.4.1.4 | 4.356 | 2 |
LCG-1 m/w to agreed 10 Tier 1 sites deployed | 15-07-2003 | More Info | |
| 1.4.1.6 | 4.956 | 2 |
LCG-1 certified and commissioned | 01-08-2003 | More Info | |
| 1.4.1.7 | 4.358 | 2 |
Experiment verification of LCG-1 (to be defined) | 01-10-2003 | More Info | |
| 1.4.2 |
Full Operational LCG-1 Service | |||||
| 1.4.2.2 | 4.957 | 2 |
LCG-1 performance goals defined | 01-09-2003 | More Info | |
| 1.4.2.3 |
Expand Service to include Tier2 centres | |||||
| 1.4.2.3.1 | 4.958 | 2 |
Tier2 centres included in service | 31-10-2003 | More Info | |
| 1.4.2.4 |
Middleware functionality complete | |||||
| 1.4.2.4.6 | 4.965 | 2 |
Middleware functionality complete | 01-10-2003 | More Info | |
| 1.4.2.5 | 4.369 | 2 |
Job Execution model defined | 30-09-2003 | More Info | |
| 1.4.2.6 | 4.370 | 2 |
Second prototype Operations and User Support Service operational | 30-10-2003 | More Info | |
| 1.4.2.8 | 4.963 | 2 |
Deployed to agreed sites | 15-10-2003 | More Info | |
| 1.4.2.9 |
Security Procedures for 2004 in place | |||||
| 1.4.2.9.3 | 4.969 | 2 |
Security Procedures for 2004 in place | 01-12-2003 | More Info | |
| 1.4.2.11 | 4.966 | 2 |
Service Review completed | 24-11-2003 | More Info | |
| M1.4 | M1.4 | 2 |
LCG-1 Service fully operational | 28-11-2003 | More Info | |
| 1.4.3 |
Fully Operational LCG-3 Service | More Info | ||||
| 1.4.3.2 | 4.961 | 2 |
LCG-3 functionality defined | 31-03-2004 | More Info | |
| 1.4.3.3 | 4.378 | 2 |
LCG-3 Pilot system available | 01-07-2004 | More Info | |
| 1.4.3.5 | 4.962 | 2 |
LCG-2 upgraded to LCG-3 | 17-01-2005 | More Info | |
| M1.6 | M1.6 | 1 |
LCG-3 Service fully operational | 28-01-2005 | More Info | |
| 1.4.4 |
Completion of Computing Service TDR | |||||
| 1.4.4.2 | 4.382 | 2 |
Experience with LCG-2 reviewed | 01-07-2005 | More Info | |
| M1.8 | M1.8 | 1 |
Completion of Computing Service TDR | 30-06-2005 | More Info | |
|
Level-1 Milestones |
||||||
| WBS | ID_Unique | MS_Lvl |
Name |
Date_MS | MS_Done | Hyperlink |
| 1.5 |
Global Milestones/Goals/Targets | |||||
| M1.1 |
First Global Service - Initial Availability | |||||
| M1.1 | M1.1 | 1 |
First Global Service (LCG-1) - Initial Availability | 01-07-2003 | More Info | |
| M1.2 | M1.2 | 1 |
General release of POOL hybrid data store | 02-06-2003 | 30-06-2003 | More Info |
| M1.3 | M1.3 | 1 |
Distributed production environment using grid services | 03-11-2003 | More Info | |
| M1.4 |
Fully Operational LCG-1 Service | More Info | ||||
| M1.4 | M1.4 | 1 |
Fully operational LCG-1 Service | 28-11-2003 | More Info | |
| M1.5 | M1.5 | 1 |
Distributed end-user analysis from a Tier-3 Regional Centre | 03-05-2004 | More Info | |
| M1.6 |
Fully Operational LCG-3 Service | More Info | ||||
| 1.5.6.1 | 5.401 | 0 |
Define LCG-3 | 02-02-2004 | ||
| 1.5.6.2 | 5.402 | 0 |
LCG-3 pilot system available | 01-07-2004 | ||
| 1.5.6.3 | 5.403 | 0 |
Decision on new batch system software (CERN)
| 31-12-2004 | ||
| M1.6 | M1.6 | 1 |
Fully operational LCG-3 Service | 28-01-2005 | More Info | |
| M1.7 | M1.7 | 1 |
Full function release of persistency framework | 01-03-2005 | More Info | |
| M1.8 |
Completion of the Computing Service TDR | More Info | ||||
| M1.8 | M1.8 | 1 |
Completion of Computing Service TDR | 30-06-2005 | More Info | |