Version 2004.04/V1
This is a summary of the Level-1 and Level-2 Milestones for the LHC Computing Grid Project LCG as presented in the quarterly report of April 2004 covering the period of January to March 2004.
Applications
Fabrics
GRID Technology
GRID Deployment
Middleware
ARDA
Level-1 Milestones
The Level-1 and Level-2
Milestones constitute the baseline planning for the LCG.
The unique identifier is in column 2.
The comment in column 3 indicates the introduction date of milestones or
experiment verification milestones.
The column 5 (Date_MS) gives the baseline date when
the milestone is due and column 6 (MS_Done) gives the
date when a milestone was achieved.
Hyperlinks to more detailed
information (column 7) are currently available for the applications and grid
deployment areas and for the Level-1 milestones. For the rest this information
will be provided in the near future.
Full planning information is available as MS-Project
file.
More information is available in the Milestones Report Q4/2003 (.doc)
|
WBS |
ID_Unique |
Comment |
Name |
Date_MS |
MS_Done |
Hyperlink |
|
1 |
|
___ |
LHC Computing Grid Project |
|
|
|
|
1.1 |
|
|
Applications |
|
|
|
|
1.1 |
1.3 |
|
Development, support and resource plan through
2008 |
31-12-04 |
|
|
|
1.1 |
1.4 |
|
Phase 1 AA software complete and deployed |
30-09-05 |
|
|
|
1.1.1 |
|
|
Software Process and Infrastructure (SPI) |
|
|
|
|
1.1.1 |
1.16 |
|
Initial process and infrastructure team in place |
15-04-02 |
14-07-02 |
|
|
1.1.1 |
1.16 |
|
Basic LCG code development and repository
services in place |
01-05-02 |
02-05-02 |
|
|
1.1.1 |
1.16 |
|
Software process workplan
to SC2 |
11-10-02 |
11-10-02 |
|
|
1.1.1 |
1.16 |
|
All infrastructure tools and services in beta |
31-12-02 |
09-02-03 |
|
|
1.1.1 |
1.16 |
|
All infrastructure tools and services released
(SPI V1.0) |
28-02-03 |
28-02-03 |
|
|
1.1.1 |
1.16 |
|
2003 SPI workplan
complete |
30-05-03 |
29-06-03 |
|
|
1.1.1 |
1.16 |
|
Software library complete |
31-05-03 |
01-05-03 |
|
|
1.1.1 |
1.16 |
|
|
31-05-03 |
22-12-02 |
|
|
1.1.1 |
1.17 |
|
SPI support for Windows binary version of LCG
software |
15-08-03 |
15-08-03 |
|
|
1.1.1 |
1.19 |
|
SPI tools operational on IT CVS service |
30-11-03 |
29-01-04 |
|
|
1.1.1 |
1.2 |
i_jan04 |
savannah.cern.ch migrated to GNU savannah |
20-02-04 |
04-02-04 |
|
|
1.1.1 |
1.22 |
i_apr04 |
RH 7.3 gcc 3.2.3
supported |
15-05-04 |
|
|
|
1.1.1 |
1.21 |
i_apr04 |
SPI/EGEE collaborative workplan
complete |
31-05-04 |
|
|
|
1.1.1 |
1.22 |
i_apr04 |
Certification of external software for the new
Linux platform |
01-07-04 |
|
|
|
1.1.1 |
1.2 |
i_jan04 |
LCG AA build system selection |
15-07-04 |
|
|
|
1.1.2 |
|
|
Physics data management |
|
|
|
|
1.1.2 |
1.1 |
|
Persistency framework workplan
to SC2 |
12-07-02 |
02-08-02 |
|
|
1.1.2 |
1.11 |
|
2003 persistency framework workplan
complete |
24-02-03 |
05-03-03 |
|
|
1.1.2 |
1.2 |
|
General release of POOL hybrid data store |
15-06-03 |
30-06-03 |
|
|
1.1.2 |
1.12 |
|
2004 persistency framework workplan
complete |
15-12-03 |
03-04-04 |
|
|
1.1.2.1 |
|
|
POOL Persistency Framework |
|
|
|
|
1.1.2.1 |
1.1 |
|
Hybrid event store workshop |
05-06-02 |
05-06-02 |
|
|
1.1.2.1 |
1.1 |
|
Persistency framework status report |
18-06-02 |
18-06-02 |
|
|
1.1.2.1 |
1.1 |
|
V0.1 POOL internal release |
30-09-02 |
02-10-02 |
|
|
1.1.2.1 |
1.11 |
|
V0.2 POOL internal release |
31-10-02 |
15-11-02 |
|
|
1.1.2.1 |
1.11 |
|
First prototype (V0.3) release of POOL hybrid
data store |
15-12-02 |
18-12-02 |
|
|
1.1.2.1 |
1.11 |
|
SPI compliance of POOL |
28-02-03 |
07-03-03 |
|
|
1.1.2.1 |
1.11 |
|
POOL V0.4 'interface-complete' release |
28-02-03 |
07-03-03 |
|
|
1.1.2.1 |
1.11 |
|
Define feature set of first general release of
POOL |
01-03-03 |
05-03-03 |
|
|
1.1.2.1 |
1.11 |
|
POOL V1.0 pre-production release |
30-04-03 |
13-05-03 |
|
|
1.1.2.1 |
1.11 |
|
Nightly builds deployed in POOL |
30-05-03 |
29-06-03 |
|
|
1.1.2.1 |
1.18 |
|
CMS POOL integration: POOL persistency of CMS
event |
31-07-03 |
31-07-03 |
|
|
1.1.2.1 |
1.18 |
|
ATLAS POOL integration: POOL persistency in
Release 7 |
10-09-03 |
11-09-03 |
|
|
1.1.2.1 |
1.12 |
|
POOL RDBMS independence layer in beta |
30-09-03 |
02-01-04 |
|
|
1.1.2.1 |
1.18 |
|
POOL support for Windows binaries |
30-09-03 |
23-01-04 |
|
|
1.1.2.1 |
1.11 |
|
Initial POOL deployment on LCG-1 |
15-11-03 |
24-11-03 |
|
|
1.1.2.1 |
1.12 |
|
POOL hierarchical cataloging
production release |
15-03-04 |
09-03-04 |
|
|
1.1.2.1 |
1.22 |
|
POOL RDBMS abstraction layer completed |
31-05-04 |
|
|
|
1.1.2.1 |
1.22 |
|
RDBMS independency achieved for POOL relational
components |
30-06-04 |
|
|
|
1.1.2.1 |
1.22 |
|
First release of the POOL Relational Storage
Manager |
31-08-04 |
|
|
|
1.1.2.1 |
1.12 |
|
POOL meets scalability requirements |
31-10-04 |
|
|
|
1.1.2.1 |
1.22 |
|
POOL integrates ROOT4 |
31-10-04 |
|
|
|
1.1.2.1 |
1.22 |
|
Full function release of POOL persistency
framework |
01-03-05 |
|
|
|
1.1.2.2 |
|
|
Conditions database |
|
|
|
|
1.1.2.2 |
1.22 |
i_apr04 |
Common interface for Conditions DB defined |
30-06-04 |
|
|
|
1.1.2.2 |
1.22 |
i_apr04 |
Conditions DB production release |
31-07-04 |
|
|
|
1.1.3 |
|
|
Core libraries and services (SEAL) |
|
|
|
|
1.1.3 |
1.12 |
|
Establish core libraries and services (SEAL)
project |
30-10-02 |
30-10-02 |
|
|
1.1.3 |
1.13 |
|
Define the V1 SEAL software suite |
30-11-02 |
30-11-02 |
|
|
1.1.3 |
1.11 |
|
Prototype object dictionary service released |
01-12-02 |
18-12-02 |
|
|
1.1.3 |
1.13 |
|
Present the initial SEAL workplan
to SC2 |
10-01-03 |
10-01-03 |
|
|
1.1.3 |
1.13 |
|
SEAL V1 essentials in alpha |
31-03-03 |
07-04-03 |
|
|
1.1.3 |
1.13 |
|
SEAL V0.3 internal release |
16-05-03 |
24-05-03 |
|
|
1.1.3 |
1.13 |
|
Nightly builds deployed in SEAL |
30-06-03 |
10-07-03 |
|
|
1.1.3 |
1.13 |
|
SEAL V1 release |
30-06-03 |
18-07-03 |
|
|
1.1.3 |
1.19 |
|
SEAL support for Windows binaries |
15-09-03 |
09-10-03 |
|
|
1.1.3 |
1.2 |
i_apr04 |
External software guideline document |
31-05-04 |
|
|
|
1.1.3 |
1.2 |
i_apr04 |
Workbook for SEAL |
15-06-04 |
|
|
|
1.1.3 |
1.21 |
i_apr04 |
New Dictionary API and reference implementation |
30-06-04 |
|
|
|
1.1.3.8 |
|
|
Mathematical libraries |
|
|
|
|
1.1.3.8 |
1.17 |
|
Delivery of first round of GSL enhancements |
30-05-03 |
30-05-03 |
|
|
1.1.3.8 |
1.18 |
|
Math library workplan
in place |
31-07-03 |
27-03-04 |
|
|
1.1.3.8 |
1.12 |
|
Statement on GSL and NAG usage for math library |
30-09-03 |
24-10-03 |
|
|
1.1.3.8 |
1.21 |
|
mathlib
project web |
15-07-04 |
|
|
|
1.1.3.8 |
1.21 |
|
First version of the C++ mathlib
package |
01-10-04 |
|
|
|
1.1.4 |
|
|
Physicist Interface (PI) |
|
|
|
|
1.1.4 |
1.15 |
|
Establish physicist interface project |
19-11-02 |
25-11-02 |
|
|
1.1.4 |
1.15 |
|
Report on PI experiment consultations |
20-01-03 |
20-01-03 |
|
|
1.1.4 |
1.15 |
|
Initial PI plan presented to SC2 |
29-01-03 |
07-02-03 |
|
|
1.1.4 |
1.15 |
|
Physicist interface (PI) workplan
completed |
01-07-03 |
04-07-03 |
|
|
1.1.4.1 |
|
|
Analysis services |
|
|
|
|
1.1.4.1 |
1.15 |
|
AIDA interface review (developers) completed |
30-05-03 |
30-05-03 |
|
|
1.1.4.1 |
1.17 |
|
AIDA interface review (users) completed |
15-09-03 |
09-10-03 |
|
|
1.1.5 |
|
|
Simulation |
|
|
|
|
1.1.5 |
1.13 |
|
SC2 mandate for simulation project |
07-12-02 |
07-12-02 |
|
|
1.1.5 |
1.13 |
|
Simulation project structure defined |
28-01-03 |
28-01-03 |
|
|
1.1.5 |
1.13 |
|
Simulation project draft workplan |
28-02-03 |
28-02-03 |
|
|
1.1.5 |
1.13 |
|
Simulation project initial workplan
approved |
14-03-03 |
19-03-03 |
|
|
1.1.5.1 |
|
|
Generic simulation framework |
|
|
|
|
1.1.5.1 |
1.14 |
|
Generic simulation framework prototype available
(G4 and FLUKA) |
31-12-03 |
|
|
|
1.1.5.2 |
|
|
Geant4 development and integration |
|
|
|
|
1.1.5.2 |
1.19 |
|
SPI-G4 collaborative infrastructure pilot |
16-02-04 |
16-02-04 |
|
|
1.1.5.2 |
1.21 |
i_apr04 |
Geant4 6.2 release - resource usage refinements |
25-06-04 |
|
|
|
1.1.5.2 |
1.21 |
i_apr04 |
Consolidated Geant4 acceptance
suite for LHC |
15-10-04 |
|
|
|
1.1.5.2 |
1.21 |
i_apr04 |
Geant4 7.0 release - physics models and geometry |
17-12-04 |
|
|
|
1.1.5.4 |
|
|
Physics validation |
|
|
|
|
1.1.5.4 |
1.14 |
|
Test beam setup of the four experiments available
in G4 |
31-05-03 |
31-05-03 |
|
|
1.1.5.4 |
1.14 |
|
First cycle of EM physics validation complete |
30-09-03 |
30-09-03 |
|
|
1.1.5.4 |
1.14 |
|
Simulation physics requirements revisited |
31-12-03 |
25-02-04 |
|
|
1.1.5.4 |
1.15 |
|
First cycle of hadronic
physics validation complete |
01-02-04 |
|
|
|
1.1.5.4 |
1.21 |
i_apr04 |
Review/prioritization of simple benchmarks for simu physics validation |
31-05-04 |
|
|
|
1.1.5.4 |
1.21 |
i_apr04 |
Comparison of LHC calorimeters for EM shower
development |
15-09-04 |
|
|
|
1.1.5.4 |
1.22 |
i_apr04 |
Second iteration of hadronic
physics validation complete |
15-10-04 |
|
|
|
1.1.5.4 |
1.15 |
|
Simulation test and benchmark suite available |
31-12-04 |
|
|
|
1.1.5.4 |
1.15 |
|
Final physics validation document complete |
31-12-04 |
|
|
|
1.1.5.6 |
|
|
Generator services |
|
|
|
|
1.1.5.6 |
1.14 |
|
Generator librarian and alpha version of support
infrastructure in place |
30-06-03 |
30-06-03 |
|
|
1.1.5.6 |
1.2 |
|
Agreement on formats for event generator common
samples |
01-03-04 |
01-03-04 |
|
|
1.1.5.6 |
1.2 |
|
Beta version of MCDB in production in the LCG
environment |
01-07-04 |
|
|
|
1.1.5.6 |
1.2 |
i_apr04 |
Agreement on parton-level
event generator file format |
01-09-04 |
|
|
|
1.1.5.6 |
1.21 |
i_apr04 |
Generator production framework beta |
01-12-04 |
|
|
|
|
|
|
Experiment verification milestones - AA |
|
|
|
|
1.1.2.1 |
1.18 |
V_CMS |
CMS POOL integration: POOL persistency of CMS
event |
31-07-03 |
31-07-03 |
|
|
1.1.2.1 |
1.18 |
V_ATLAS |
ATLAS POOL integration: POOL persistency in
Release 7 |
10-09-03 |
11-09-03 |
|
|
1.1.2.1 |
1.18 |
V_CMS |
CMS POOL validation with PCP data |
31-10-03 |
21-10-03 |
|
|
1.1.2.1 |
10198 |
V_LHCb |
LHCb POOL integration: Gaudi persistency replaced
by POOL |
19-12-03 |
04-02-04 |
|
|
1.1.2.1 |
10196 |
V_ATLAS |
ATLAS POOL validation with DC1 data |
19-01-04 |
|
|
|
1.1.2.1 |
10199 |
V_ATLAS |
ATLAS validation of POOL Metadata/event
collections |
01-02-04 |
|
|
|
1.1.2.1 |
10197 |
V_ATLAS |
ATLAS POOL validation with complete Event Data
Model |
01-04-04 |
|
|
|
1.1.3 |
10201 |
V_LHCb |
LHCb integration: SEAL plugin
manager integrated in Gaudi |
19-12-03 |
|
|
|
1.1.3 |
10200 |
V_ATLAS |
ATLAS integration: SEAL Integration into Athena |
31-12-03 |
|
|
|
1.1.4 |
10202 |
V_ATLAS |
ATLAS int: ROOT
implementation of AIDA histograms in Athena |
30-11-03 |
30-11-03 |
|
|
1.1.5.1 |
10203 |
V_ATLAS |
ATLAS int: Generic
simulation framework validated by ATLAS |
01-05-04 |
|
|
WBS |
ID_Unique |
Comment |
Name |
Date_MS |
MS_Done |
Hyperlink |
|
1.2 |
|
___ |
Fabrics |
|
|
|
|
1.2.1 |
|
|
Repositories and Managed Storage |
|
|
|
|
1.2.1.1 |
|
|
Castor |
|
|
|
|
1.2.1.1.1 |
2.521 |
|
Concept of pluggable scheduler and high rate
request handling demonstrated |
01-10-03 |
22-10-03 |
|
|
1.2.1.1.2 |
2.52 |
|
Integrated prototype of the whole system |
02-02-04 |
|
|
|
1.2.1.1.3 |
2.519 |
|
Production system ready for deployment |
01-04-04 |
|
|
|
1.2.1.1.4 |
2.518 |
|
Full functional CASTOR release available |
01-03-05 |
|
|
|
1.2.1.1.5 |
2.1167 |
V_ATLAS |
Full CASTOR support for ATLAS DC3 (2nd half 2005) |
30-06-05 |
|
|
|
1.2.1.2 |
|
|
Data Recording Challenges |
|
|
|
|
1.2.1.2.1 |
2.516 |
V_ALICE |
|
01-10-03 |
|
|
|
1.2.1.2.2 |
2.117 |
V_ALICE |
ALICE Verification of target performance for ADC
V |
15-11-03 |
|
|
|
1.2.1.2.3 |
2.515 |
V_ALICE |
|
01-10-04 |
|
|
|
1.2.1.2.4 |
2.1172 |
V_ALICE |
ALICE Verification of target performance for ADC
VI |
15-11-04 |
|
|
|
1.2.1.2.5 |
2.514 |
V_ALICE |
|
03-10-05 |
|
|
|
1.2.1.2.6 |
2.1173 |
V_ALICE |
ALICE Verification of target performance for ADC
VII |
15-11-05 |
|
|
|
1.2.1.3 |
|
|
Evaluation of new tape hardware |
|
|
|
|
1.2.1.3.1 |
2.526 |
|
Report on LTO evaluation delivered |
01-03-04 |
|
|
|
1.2.1.3.2 |
2.525 |
|
Report on high-end tape drive evaluation
delivered |
01-12-04 |
|
|
|
1.2.1.3.3 |
2.524 |
|
Proposal on storage architecture and implementation
of disk storage system for Phase 2 made |
01-06-04 |
|
|
|
1.2.2 |
|
|
Fabric Management |
|
|
|
|
1.2.2.1 |
2.538 |
|
SPMA – full production |
01-08-03 |
18-08-03 |
|
|
1.2.2.2 |
2.537 |
|
NCM – full production |
03-11-03 |
03-11-03 |
|
|
1.2.2.3 |
2.536 |
|
SMS – initial system |
01-10-03 |
01-10-03 |
|
|
1.2.2.4 |
2.535 |
|
SMS – full production |
01-07-04 |
|
|
|
1.2.2.5 |
2.534 |
|
Monitoring – Systems monitor displays operational |
01-10-03 |
|
|
|
1.2.2.6 |
2.533 |
|
Monitoring – No further need for private
(experiment) monitoring |
01-03-04 |
30-03-04 |
|
|
1.2.2.7 |
2.532 |
|
FT – development started |
01-09-03 |
01-09-03 |
|
|
1.2.2.8 |
2.531 |
|
FT – Initial system available |
01-03-04 |
01-03-04 |
|
|
1.2.2.9 |
2.53 |
|
FT – Deployment complete |
01-09-04 |
|
|
|
1.2.2.10 |
2.529 |
|
HSM ops display – development started |
01-10-03 |
01-10-03 |
|
|
1.2.2.11 |
2.528 |
|
HSM ops display – system complete |
01-12-04 |
|
|
|
1.2.3 |
|
|
Computer Centre Upgrade |
|
|
|
|
1.2.3.1 |
2.553 |
|
Vault converted to machine room |
01-11-02 |
01-11-02 |
|
|
1.2.3.2 |
2.552 |
|
Right half of m/c room migrated to vault |
01-08-03 |
15-08-03 |
|
|
1.2.3.3 |
2.551 |
|
Sub-station civil engineering starts |
01-09-03 |
18-08-03 |
|
|
1.2.3.4 |
2.55 |
|
Sub-station civil engineering finishes |
01-03-04 |
01-03-04 |
|
|
1.2.3.5 |
2.549 |
|
Sub-station electrical installation starts |
01-04-04 |
|
|
|
1.2.3.6 |
2.548 |
|
Sub-station commissioned |
07-01-05 |
|
|
|
1.2.3.7 |
2.547 |
|
Electrical distribution on right side of m/c room
upgraded |
02-02-04 |
02-02-04 |
|
|
1.2.3.8 |
2.546 |
|
Left half of m/c room emptied |
02-08-04 |
|
|
|
1.2.3.9 |
2.545 |
|
Electrical distribution on left side of m/c room
upgraded |
01-06-05 |
|
|
|
1.2.3.10 |
2.544 |
|
Machine room HVAC upgraded |
01-03-05 |
|
|
|
1.2.3.11 |
2.543 |
|
New 800KW UPS for physics installed |
03-04-06 |
|
|
|
1.2.3.12 |
2.542 |
|
Current UPS area re-modelled |
01-01-07 |
|
|
|
1.2.3.13 |
2.541 |
|
2nd 800 KW UPS added |
02-04-07 |
|
|
|
1.2.3.14 |
2.54 |
|
3rd 800 KW UPS added |
01-04-08 |
|
|
|
1.2.4 |
|
|
Batch Computing |
|
|
|
|
1.2.4.1 |
2.564 |
|
Baseline plan for Phase 2 agreed (architecture +
technology) |
01-06-04 |
|
|
|
1.2.4.2 |
|
|
Grid Integration |
|
|
|
|
1.2.4.2.1 |
2.562 |
|
10 LXBATCH nodes integrated in LCG-1 (isolated
from main LXBATCH) |
01-08-03 |
20-01-04 |
|
|
1.2.4.2.2 |
2.561 |
|
100 LXBATCH nodes integrated in LCG-1 (isolated
from main LXBATCH) |
01-10-03 |
20-01-04 |
|
|
1.2.4.2.3 |
2.56 |
|
Full integration of LXBATCH worker nodes in LCG-1
completed |
01-12-03 |
15-03-04 |
|
|
1.2.4.3 |
|
|
Batch Scheduling |
|
|
|
|
1.2.4.3.1 |
2.557 |
|
Decision on Phase 2 Batch Scheduling System made |
01-12-04 |
|
|
|
1.2.5 |
|
|
Installation Schedule (short term) |
|
|
|
|
1.2.5.9 |
|
|
Networking infrastructure |
|
|
|
|
1.2.5.9.3 |
2.58 |
|
Integration of 10 Gbit
equipment into the Prototype done |
01-07-03 |
01-07-03 |
|
|
1.2.5.9.5 |
2.582 |
|
First phase of backbone replacement by 10 Gbit equipment |
01-07-04 |
|
|
|
1.2.5.9.6 |
2.583 |
|
Backbone fully upgraded to 10 Gbit |
01-07-05 |
|
|
|
1.2.6 |
|
|
Phase 2 Acquisition Process |
|
|
|
|
1.2.6.1 |
2.591 |
|
Decisions on the equipment selection criteria
made |
01-12-03 |
01-12-03 |
|
|
1.2.6.2 |
2.59 |
|
Agreement with SPL on acquisition strategy ready |
01-12-03 |
01-12-03 |
|
|
1.2.6.3 |
2.589 |
|
Market survey issued for cpu
and disk |
01-07-04 |
|
|
|
1.2.6.4 |
2.588 |
|
Market survey issued for tape system |
01-12-04 |
|
|
|
1.2.6.5 |
2.587 |
|
Phase 2 TDR ready |
01-07-05 |
|
|
|
1.2.6.6 |
2.586 |
|
Finance Committee for cpu
& disk vendor selection passed |
01-09-05 |
|
|
|
1.2.6.7 |
2.585 |
|
Finance Committee for tape system selection
passed |
01-12-05 |
|
|
|
1.2.6.8 |
2.584 |
|
All orders placed for 2006 equipment |
01-03-06 |
|
|
|
1.2.6.9 |
2.575 |
|
Order placed for tape system |
09-01-06 |
|
|
|
1.2.6.10 |
2.574 |
|
2006 system installation and commissioning
complete |
01-08-06 |
|
|
|
1.2.6.11 |
2.573 |
|
Phase 2 service in production |
01-09-06 |
|
|
|
1.2.7 |
|
|
Milestones prior to June 2003 |
|
|
|
|
1.2.7.1 |
2.599 |
|
L2M Production Pilot I starts |
15-01-03 |
06-01-03 |
|
|
WBS |
ID_Unique |
Comment |
Name |
Date_MS |
MS_Done |
Hyperlink |
|
1.3 |
|
___ |
Grid Technology Area |
|
|
|
|
1.3.1 |
|
|
Technology Review |
|
|
|
|
1.3.1.3 |
3.496 |
|
Report on the Review of Grid Technologies 2003
ready |
06-10-03 |
06-10-03 |
|
|
1.3.1.5 |
3.498 |
|
Report on the Review of Grid Technologies 2004
ready |
02-11-04 |
|
|
|
1.3.2 |
|
|
System Modeling |
|
|
|
|
1.3.2.2 |
3.337 |
|
Modeling
plan for work during 2003 created |
15-07-03 |
15-07-03 |
|
|
1.3.3 |
|
|
LCG Technology Evolution |
|
|
|
|
1.3.3.2 |
3.344 |
|
Report on GT3 capabilities ready |
01-09-03 |
01-09-03 |
|
|
1.3.5 |
|
|
TDR Planning |
|
|
|
|
1.3.5.2 |
3.347 |
|
Plan and outline for the TDR available |
01-10-04 |
|
|
|
1.3.5.3 |
3.348 |
|
Proposal for review created |
24-02-05 |
|
|
|
1.3.6.4 |
3.1188 |
V_LHCb |
Computing model chapter of LHCb computing TDR
available |
01-12-04 |
|
|
|
1.3.5.4 |
3.349 |
|
LCG TDR completed |
01-06-05 |
|
|
|
1.3.7 |
|
|
Milestones prior to June 03 |
|
|
|
|
1.3.7.3 |
|
|
Deliver initial software packages |
|
|
|
|
1.3.7.3.2 |
3.494 |
|
Initial software packages delivered |
30-05-03 |
30-05-03 |
|
|
1.3.7.3.3 |
3.1174 |
V_ALICE |
ALICE AliEn analysis
interface to LCG-1 performance evaluation |
15-10-04 |
|
|
|
WBS |
ID_Unique |
Comment |
Name |
Date_MS |
MS_Done |
Hyperlink |
|
1.4 |
|
___ |
Grid Deployment |
|
|
|
|
1.4.1 |
|
|
First Global Service Initial Availability |
|
|
|
|
1.4.1.1 |
4.353 |
|
Initial middleware for LCG-1 delivered |
30-04-03 |
31-07-03 |
|
|
1.4.1.2 |
4.354 |
|
LCG-1 security model implemented |
30-06-03 |
30-06-03 |
|
|
1.4.1.3 |
4.355 |
|
First prototype operations & user support
service in place |
30-06-03 |
30-06-03 |
|
|
1.4.1.4 |
4.356 |
|
LCG-1 m/w to agreed 10 Tier 1 sites deployed |
15-07-03 |
15-09-03 |
|
|
1.4.1.6 |
4.956 |
|
LCG-1 certified and commissioned |
01-08-03 |
29-09-03 |
|
|
1.4.1.7 |
4.1175 |
V_ALICE |
ALICE AliEn production
interface to LCG-1 readiness review (prototype design and functionality) |
14-11-03 |
05-01-04 |
|
|
1.4.1.8 |
4.1176 |
V_ALICE |
ALICE AliEn analysis
interface to LCG-1 readiness review (prototype design and functionality) |
15-04-04 |
|
|
|
1.4.1.9 |
4.1177 |
V_ALICE |
ALICE AliEn production
interface to LCG-1 performance evaluation |
15-07-04 |
|
|
|
1.4.1.10 |
4.1178 |
V_ALICE |
ALICE LCG-1 PDC3 production environment verification |
15-07-04 |
|
|
|
1.4.1.11 |
4.1179 |
V_ALICE |
ALICE LCG-1 PDC3 analysis environment verification |
15-10-04 |
|
|
|
1.4.1.12 |
4.358 |
V_ATLAS |
ATLAS validation of LCG-1 |
15-10-04 |
|
|
|
1.4.1.13 |
4.1169 |
V_ATLAS |
ATLAS production on LCG-1 |
29-02-04 |
|
|
|
1.4.1.14 |
4.1186 |
V_LHCb |
DIRAC deployed in LCG1 |
28-11-03 |
|
|
|
1.4.1.15 |
4.1185 |
V_LHCb |
50% of LHCb DC04 production executing in LCG1 |
01-06-04 |
|
|
|
1.4.1.16 |
4.1187 |
V_LHCb |
LHCb analysis environment ( |
01-07-04 |
|
|
|
1.4.2 |
|
|
Full Operational LCG-1 Service |
|
|
|
|
1.4.2.2 |
4.957 |
|
LCG-1 performance goals defined |
01-09-03 |
09-09-03 |
|
|
1.4.2.3 |
|
|
Expand Service to include Tier2 centres |
|
|
|
|
1.4.2.3.1 |
4.958 |
|
Tier2 centres included in service |
18-10-03 |
18-10-03 |
|
|
1.4.2.4 |
|
|
Middleware functionality complete |
|
|
|
|
1.4.2.4.6 |
4.965 |
|
Middleware functionality complete |
01-10-03 |
15-12-03 |
|
|
1.4.2.5 |
4.369 |
|
Job Execution model defined |
30-09-03 |
15-09-03 |
|
|
1.4.2.8 |
4.963 |
|
Deployed to agreed sites |
15-10-03 |
15-01-04 |
|
|
1.4.2.9 |
|
|
Security Procedures for 2004 in place |
|
|
|
|
1.4.2.9.3 |
4.969 |
|
Security Procedures for 2004 in place |
30-11-03 |
10-11-03 |
|
|
1.4.2.11 |
4.966 |
|
Service Review completed (LHCC and internal
review) |
24-11-03 |
24-11-03 |
|
|
1.4.3 |
|
|
Fully Operational PDC4 environment |
|
|
More Info |
|
1.4.3.7 |
4.118 |
V_ALICE |
ALICE LCG-1 PDC4 production environment verification |
15-07-06 |
|
|
|
1.4.3.8 |
4.1181 |
V_ALICE |
ALICE LCG-1 PDC4 analysis environment verification |
15-10-06 |
|
|
|
1.4.4 |
|
|
Completion of Computing Service TDR |
|
|
|
|
1.4.4.2 |
4.382 |
|
Experience with LCG-2 reviewed |
01-07-05 |
|
|
|
1.4.5 |
|
|
LCG-2 in 2004 |
|
|
|
|
1.4.5.1 |
|
|
Service |
|
|
|
|
1.4.5.1.1 |
4.164 |
i_jan04 |
LCG-1 Fully operational: LCG-2 operational at
Core sites |
01-02-04 |
15-02-04 |
|
|
1.4.5.1.2 |
4.1639 |
i_jan04 |
30 day verification run successfully terminated |
15-03-04 |
30-03-04 |
|
|
1.4.5.1.3 |
4.1638 |
i_jan04 |
LCG-2 operational at 30 sites |
01-05-04 |
|
|
|
1.4.5.1.4 |
4.1637 |
i_jan04 |
50% prototype available |
20-12-04 |
|
|
|
1.4.5.2 |
|
|
Operations |
|
|
|
|
1.4.5.2.1 |
4.1635 |
i_jan04 |
Basic accounting service in place |
01-03-04 |
30-03-04 |
|
|
1.4.5.2.2 |
4.1634 |
i_jan04 |
Second GOC in operation |
01-06-04 |
30-03-04 |
|
|
1.4.5.3 |
|
|
Support |
|
|
|
|
1.4.5.3.1 |
4.1632 |
i_jan04 |
FZK Support portal as front line user support
operational |
01-06-04 |
|
|
|
1.4.5.4 |
|
|
Experiment verification of LCG-2 |
|
|
|
|
1.4.5.4.1 |
4.163 |
i_jan04 |
Report on ALICE DC initial experience |
01-04-04 |
|
|
|
1.4.5.4.2 |
4.1629 |
i_jan04 |
Report on CMS DC04 initial experience |
01-05-04 |
|
|
|
1.4.5.4.3 |
4.1628 |
i_jan04 |
Report on ATLAS initial experience |
01-05-04 |
|
|
|
1.4.5.4.4 |
4.1627 |
i_jan04 |
Report on LHCb initial experience |
01-05-04 |
|
|
|
1.4.5.5 |
|
|
Middleware |
|
|
|
|
1.4.5.5.1 |
4.1644 |
i_jan04 |
WN middleware ported to RHEL, report on ease of porting
to other OSs |
01-05-04 |
|
|
|
1.4.5.5.2 |
4.1643 |
i_jan04 |
Configuration tool available |
01-07-04 |
|
|
|
1.4.5.5.3 |
4.1642 |
i_jan04 |
Replica Manager upgrade |
01-08-04 |
|
|
WBS |
ID_Unique |
Comment |
Name |
Date_MS |
MS_Done |
Hyperlink |
|
1.5 |
|
___ |
Middleware |
|
|
|
|
1.3.4 |
|
|
LCG - EGEE Coordination |
|
|
|
|
1.3.4.1 |
3.1657 |
|
EGEE senior management appointed |
15-07-03 |
15-07-03 |
|
|
1.3.4.2 |
3.1658 |
|
Technical design team established |
01-09-03 |
04-12-03 |
|
|
1.3.4.8 |
3.1659 |
i_jan04 |
EGEE Middleware people hired |
29-02-04 |
23-03-04 |
|
|
1.3.4.9 |
3.166 |
i_jan04 |
EGEE Middleware execution plan available |
29-02-04 |
17-03-04 |
|
|
1.3.4.10 |
3.1661 |
i_jan04 |
EGEE Contract signed |
01-04-04 |
01-04-04 |
|
|
1.5.2.6 |
5.1912 |
i_apr04 |
First version of prototype available for
experiments |
16-06-04 |
|
|
|
1.5.2.6 |
5.1889 |
i_apr04 |
Development and integration tools deployed |
30-06-04 |
|
|
|
1.5.2.7 |
5.1888 |
i_apr04 |
Software cluster development & testing
infrastructure in place |
30-06-04 |
|
|
|
1.5.2.8 |
5.1887 |
i_apr04 |
Architecture & Planning Document for release
candidate 1 |
30-06-04 |
|
|
|
1.5.2.9 |
5.1886 |
i_apr04 |
Integration & Testing infrastructure in
place; test plan |
31-08-04 |
|
|
|
1.5.2.10 |
5.1885 |
i_apr04 |
Grid Services design document for release
candidate 1 |
31-08-04 |
|
|
|
1.5.2.12 |
5.1913 |
i_apr04 |
Second version of prototype available for
experiments |
31-08-04 |
|
|
|
1.5.2.11 |
5.1884 |
i_apr04 |
Release Candidate 1 |
31-12-04 |
|
|
|
WBS |
ID_Unique |
Comment |
Name |
Date_MS |
MS_Done |
Hyperlink |
|
1.6 |
|
___ |
ARDA |
|
|
|
|
1.3.7.2 |
3.1663 |
i_jan04 |
ARDA project organized |
31-01-04 |
19-02-04 |
|
|
|
|
|
E2E prototype definition |
|
|
|
|
1.6.2 |
6.1899 |
i_apr04 |
E2E ALICE prototype definition agreed with the
experiment |
31-05-04 |
|
|
|
1.6.3 |
6.1898 |
i_apr04 |
E2E ATLAS prototype definition agreed with the
experiment |
31-05-04 |
|
|
|
1.6.4 |
6.1897 |
i_apr04 |
E2E CMS prototype definition agreed with the
experiment |
31-05-04 |
|
|
|
1.6.5 |
6.1896 |
i_apr04 |
E2E LHCb prototype definition agreed with the
experiment |
31-05-04 |
|
|
|
|
|
|
Prototypes using basic middleware |
|
|
|
|
1.6.6 |
6.1895 |
i_apr04 |
E2E ALICE prototype using basic EGEE middleware |
30-09-04 |
|
|
|
1.6.7 |
6.1894 |
i_apr04 |
E2E ATLAS prototype using basic EGEE middleware |
30-09-04 |
|
|
|
1.6.8 |
6.1893 |
i_apr04 |
E2E CMS prototype using basic EGEE middleware |
30-09-04 |
|
|
|
1.6.9 |
6.1892 |
i_apr04 |
E2E LHCb prototype using basic EGEE middleware |
30-09-04 |
|
|
|
|
|
|
Prototypes capable of analysis |
|
|
|
|
1.6.14 |
6.1904 |
i_apr04 |
E2E prototype for ALICE, capable of analysis |
31-12-04 |
|
|
|
1.6.15 |
6.1903 |
i_apr04 |
E2E prototype for ATLAS, capable of analysis |
31-12-04 |
|
|
|
1.6.16 |
6.1902 |
i_apr04 |
E2E prototype for CMS, capable of analysis |
31-12-04 |
|
|
|
1.6.17 |
6.1901 |
i_apr04 |
E2E prototype for LHCb, capable of analysis |
31-12-04 |
|
|
|
1.6.18 |
6.19 |
i_apr04 |
E2E prototype for each experiment (4 prototypes),
capable of analysis (or advanced production) |
31-12-04 |
|
|
|
1.6.19 |
6.189 |
i_apr04 |
E2E prototype for each experiments (4
prototypes), capable of analysis and production |
31-12-05 |
|
|
|
WBS |
ID_Unique |
Comment |
Name |
Date_MS |
MS_Done |
Hyperlink |
|
1.9 |
|
___ |
LCG Level-1 Milestones |
|
|
|
|
M1.1 |
M1.1 |
|
First Global Service (LCG-1) - Initial
Availability |
01-07-03 |
15-09-03 |
|
|
M1.2 |
M1.2 |
|
General release of POOL hybrid data store |
02-06-03 |
30-06-03 |
|
|
M1.4 |
M1.4 |
|
Fully operational LCG-1 Service |
28-11-03 |
01-03-04 |
|
|
M1.5 |
M1.5 |
i_apr04 |
Baseline plan for Phase 2 agreed (Tier-0 &
Tier-1s) |
31-10-04 |
|
|
|
M1.6 |
M1.6 |
i_apr04 |
AA development & support plan & resources
through 2008 |
31-12-04 |
|
|
|
M1.7 |
M1.7 |
i_apr04 |
Baseline distributed batch environment using grid
service - four experiments using LCG-2 level of functionality (general batch
analysis service going beyond MC production) |
31-12-04 |
|
|
|
M1.8 |
M1.8 |
i_apr04 |
Distributed end-user batch and interactive
analysis prototype (ARDA) available and successfully tested in four
experiments |
31-12-04 |
|
|
|
M1.9 |
M1.9 |
i_apr04 |
|
31-12-04 |
|
|
|
M1.10 |
M1.10 |
i_apr04 |
Coherent operation of the LHC computing Tier-1
centres |
31-07-05 |
|
|
|
M1.11 |
M1.11 |
|
Computing service TDR |
31-07-05 |
|
|
|
M1.12 |
M1.12 |
i_apr04 |
Phase 1 applications area software – full
required functionality – available and successfully used in ATLAS, CMS &
LHCb |
30-09-04 |
|
|
|
M1.13 |
M1.13 |
i_apr04 |
|
31-12-04 |
|
|
|
M1.14 |
M1.14 |
i_apr04 |
Initial production LCG middleware providing the
functionality for the first LHC data taking in operation (Tier-0, Tier-1
Tier-2) |
30-04-06 |
|
|
|
M1.15 |
M1.15 |
i_apr04 |
Initial LCG system functionality for first LHC
run complete (Tier-0 & Tier-1s) |
31-10-06 |
|